L-Ami-Fiduciaire/_bmad-output/implementation-artifacts/epic-2-retro-2026-03-24.md
Saad Zoubir ff92311994 feat: add retrospective intelligence to create-story workflow
Load all retrospective files during story creation to carry forward
lessons learned, open action items, architecture corrections, and
deferred code review items. Fulfills Epic 2 retro action item A1.

Also includes Epic 2 retrospective and sprint status updates.

Co-Authored-By: Claude Opus 4.6 (1M context) <noreply@anthropic.com>
2026-03-24 10:56:14 +01:00

12 KiB
Raw Blame History

Epic 2 Retrospective — Role-Driven Dashboard & Command Center

Date: 2026-03-24 Facilitator: Bob (Scrum Master) Epic: 2 — Role-Driven Dashboard & Command Center Status: Complete (4/4 stories done) Previous Retrospective: Epic 1 (2026-03-20)


Team Participants

  • Bob (Scrum Master) — Facilitator
  • Alice / John (Product Owner/PM) — Product perspective
  • Charlie / Amelia (Senior Dev / Developer) — Implementation insights
  • Dana / Quinn (QA Engineer) — Quality perspective
  • Elena (Junior Dev) — Learning perspective
  • Winston (Architect) — Architecture decisions
  • Saad (Project Lead) — Direction & decisions

Epic Summary & Metrics

Delivery:

  • Stories Completed: 4/4 (100%)
  • Test Suite Growth: 182 → 222 tests (+40 new, +22%)
  • Assertions Growth: 677 → 1127+ (+66%)
  • Code Review Findings: 3 deferred items (D-1, D-2, D-3) from adversarial 3-layer review on Story 2.3
  • Blockers: 0
  • Production Incidents: 0
  • Execution Time: ~3 days (March 2022, 2026)

Stories Delivered:

Story Title Key Outcome
2.1 Owner/Manager Command Center Dashboard DashboardController rewrite, StatCard component, KPI grid, Redis cached aggregation, 11 new tests
2.2 Priority Alerts Panel 3-tier severity alerts (critical/warning/info), PriorityAlertsPanel component, 10 new tests
2.3 Worker Scoped Dashboard Worker subtitle, EmptyState, hidden assignee column, isWorker prop, 9 new tests
2.4 Dashboard Activity Feed Spatie Activity Log feed, ActivityFeed component, French relative timestamps, responsive 2-column layout, 7 new tests

FRs Covered: FR24 (KPI Dashboard), FR25 (Worker Dashboard), FR26 (Priority Alerts), FR52-FR55 (Activity Feed — dashboard panel only) NFRs Addressed: NFR5 (3-second render), NFR12 (audit trail via activity feed)


What Went Well

  1. Context management across stories was excellent. Rich story specs with "Previous Story Intelligence" sections meant each story started with full awareness of prior learnings. The due_date vs deadline gotcha was caught once in Story 2.1 and proactively avoided in all 3 subsequent stories.

  2. Strong foundations compound. The forUser() scope built in Epic 1 (Story 1.5) made Worker scoping in Story 2.3 effortless — zero debug issues, zero backend query changes needed. The cleanest story in the epic.

  3. Incremental extension pattern worked perfectly. All 4 stories cleanly extended the same DashboardController and Cache::remember() block. Story 2.1 built the foundation, 2.2 added alerts, 2.3 tweaked for Workers, 2.4 added the feed — no story broke a previous one.

  4. 100% completion with zero blockers. 4 stories in ~3 days, all acceptance criteria met, all tests passing, all code linted. Stories 2.12.3 shipped on the same day (March 20).

  5. Adversarial code review on Story 2.3 surfaced valuable deferred items. 3 documented findings (D-1 nudge/reassign, D-2 assignee param, D-3 cache invalidation) — all correctly scoped to future epics rather than blocking current work.

  6. README cold-start guide and epic status discipline delivered. Both commitments from Epic 1 retro were completed and proved their value during Epic 2.


What Didn't Go Well

  1. 15 pre-existing test failures surfaced in Story 2.4. 14 Folder feature tests with missing routes/tables + 1 WorkerDashboardTest session edge case. These have been accumulating since Epic 0 and have now been flagged for THREE retrospectives. The number is growing, not shrinking.

  2. Architecture doc drift. deadline vs due_date column name mismatch, non-existent Declaration::workspace() scope, undocumented mise_en_demeure status — flagged in 4/4 stories. Story specs compensated with "CRITICAL" notes, but source docs remain stale.

  3. Story 2.4 environment friction. Windows Docker stdin hang, Vite manifest missing in tests, duplicate function name conflict — all infrastructure issues, not code logic. Cross-platform (Windows vs Linux) friction is an ongoing environmental challenge.

  4. withoutVite() global workaround. Added to Pest.php to fix Vite manifest issue — works but could mask real Vite build problems in future tests. Documented as known debt.

  5. 2 of 5 Epic 1 action items still unresolved. A4 (pre-existing test failures) and A5 (withPivot documentation) were not addressed during Epic 2.


Key Insights & Lessons Learned

  1. Context management is the team's superpower. Investing in rich story context (Previous Story Intelligence, architecture constraints, code patterns) pays off exponentially across an epic. Small errors are expected — the system self-corrects when context is strong.

  2. Load retrospective files as context during story creation. Saad's process fix: with Opus 4.6's 1M token window, loading a retro file during story creation is essentially free and organically carries forward lessons learned, action items, and architecture corrections into every new story spec.

  3. Pre-existing test failures must be resolved within the same epic. No more carrying debt across retros. Three-retro flags indicate a systemic accountability gap.

  4. Strong foundations compound — invest early. The forUser() scope, Cache::remember() pattern, and role-based shared props from Epics 0-1 made Epic 2 dramatically smoother. Each epic should leave foundations for the next.

  5. Cross-platform friction is environmental, not architectural. Windows vs Linux differences cause occasional debugging overhead. Document workarounds and move on — don't over-engineer solutions.


Previous Retrospective (Epic 1) Follow-Through

# Action Item Status Evidence
A1 Create README.md with cold-start guide Completed README.md exists with Cold-Start Guide, Vite gotcha, verification checklist
A2 Update epic-1 to done in sprint-status.yaml Completed sprint-status.yaml shows epic-1: done
A3 Epic status update discipline Completed epic-2 correctly marked done after all stories done
A4 Resolve pre-existing test failures Not Addressed (3rd retro flag) 15 pre-existing failures surfaced in Story 2.4
A5 Document pivot withPivot gotchas in project-context.md Not Addressed project-context.md does not mention withPivot

Score: 3/5 completed, 0/5 in progress, 2/5 not addressed.

Key concern: A4 is now a THIRD retro flag. Made critical blocker for Epic 3.


Deferred Code Review Items (from Story 2.3 Review)

ID Description Severity Affects
D-1 Nudge/Reassign dropdown items unconditionally disabled Medium Epic 3, Story 3.2
D-2 StatCard assignee param not consumed by declarations index Low (intentional) Epic 4, Story 4.1
D-3 Cache not invalidated on role change (5-min TTL mitigates) Low Cross-cutting

Action Items

# Action Owner Priority Success Criteria
A1 Load retrospective file as context during every story creation Bob (SM) Critical Every new story spec references latest retro and incorporates relevant lessons
A2 Fix 15 pre-existing test failures (THIRD retro flag — BLOCKS Epic 3) Quinn (QA) + Amelia (Dev) Critical All 222+ tests pass with zero failures
A3 Document withPivot gotchas in project-context.md (carried from Epic 1) Amelia (Dev) Medium project-context.md contains WorkspaceUser pivot field gotchas
A4 Update architecture doc: correct deadlinedue_date and other drift Winston (Architect) Medium Architecture doc matches actual DB schema and scope names
A5 Review withoutVite() global workaround compatibility with Epic 3 Quinn (QA) Low Confirmed compatible or replaced with targeted fix
A6 Maintain epic status update discipline (proven — keep enforcing) Bob (SM) Ongoing No stale epic statuses

Team Agreements

  • Load retrospective file as context during every story creation — non-negotiable new agreement
  • Code review remains mandatory on every story — never skip it
  • "Previous Story Intelligence" sections continue in every story spec
  • Wayfinder routes remain the ONLY way to reference URLs in Vue
  • Pre-existing test failures must be resolved within the same epic — no more carrying across retros (new agreement)

Next Epic Preview — Epic 3: Collaboration, Nudge System & Notifications

Dependencies on Epic 2:

  • D-1: Dashboard nudge/reassign dropdown actions need enabling in Story 3.2
  • Activity feed Spatie Activity Log infrastructure (Story 2.4) — foundation for notification events
  • Dashboard layout stability — notification bell goes in app header, not dashboard
  • forUser() scope and role-based patterns — reused for notification scoping

Stories Planned: 5 (3.13.5)

Story Title Key Focus
3.1 Notification Infrastructure Setup notifications table, NotificationType enum, ShouldQueue patterns
3.2 One-Click Nudge System NudgeController, NudgePopover, enable D-1 dropdown
3.3 Notification Center and Bell In-app notification center with badge count
3.4 Bulk Client Notification Scheduling Document request campaigns to multiple clients
3.5 Email Notification Enhancement Mail channel for key events

Infrastructure Ready:

  • Redis queue — running (Epic 0, Story 0.4)
  • Queue worker — configured in Docker Compose
  • Spatie Activity Log — proven in Story 2.4
  • Notifiable trait — already on User model via Fortify
  • Laravel notification channels (database + mail) — framework-provided
  • Test fakes (Notification::fake(), Mail::fake()) — framework-provided

Significant Changes Required: None — Epic 2 discoveries do not change Epic 3's plan.


Preparation Tasks for Epic 3

Critical (blocks Epic 3 start):

  • Fix 15 pre-existing test failures — Owner: Quinn + Amelia
  • Update story creation process to load retro as context — Owner: Bob (SM)

Before story creation:

  • Update architecture doc drift items — Owner: Winston
  • Add withPivot gotchas to project-context.md — Owner: Amelia

Nice-to-have:

  • Confirm withoutVite() compatibility with notification tests — Owner: Quinn

Readiness Assessment

Area Status Notes
Testing & Quality Strong 222 tests, 1127+ assertions, manually verified by Saad
Deployment Expected Local dev only — production is Epic 7 scope
Stakeholder Acceptance Approved Positive feedback received: "good work"
Technical Health Stable Saad confirms codebase feels solid
Unresolved Blockers None Clean slate for Epic 3
Infrastructure Ready Redis, queue worker, notifications, mail — all in place

Verdict: Epic 2 is fully complete. Team is clear to proceed with Epic 3 after completing 2 critical path items (fix test failures + update story creation process to load retro).


Next Steps

  1. Fix 15 pre-existing test failures — critical blocker
  2. Update story creation workflow to load latest retro — critical process fix
  3. Review action items in next standup
  4. Begin Epic 3 — start creating stories with SM agent's create-story
  5. Epic will be marked as in-progress automatically when first story is created

Team Performance

Epic 2 delivered 4 stories with outstanding velocity in ~3 days. 40 new tests added, zero blockers, zero production incidents. The "morning command center" dashboard received positive stakeholder feedback. The retrospective surfaced 4 key insights and 0 significant plan-changing discoveries. The team is well-positioned for Epic 3 success.


Retrospective facilitated by Bob (Scrum Master) on 2026-03-24